Adams County, Colorado, has approved a land use request for Big Bronco Solar and Storage, a $675 million project from Lightsource bp, a solar developer owned by BP.
The county’s Board of Commissioners voted Oct. 13 to approve 2,800 acres in Watkins, east of Denver International Airport, allowing the site to operate for 40 years.
According to Rocky Mountain PBS, the project will include an 1,800-acre solar farm, a utility substation, a transmission line, and a battery storage system. The solar array is expected to generate 300 megawatts (MW), enough to power about 99,000 homes, and the batteries can deliver up to 300 MW.
Lightsource bp says the site’s location lets power flow into Denver, where most of Xcel Energy’s load is, without new transmission construction or upgrades. It also expects the project to generate about $40 million in property tax revenue for Adams County special districts and to employ up to 400 workers at peak construction, many of them hired locally.
“Power from this project can easily flow into Denver, where most of Xcel’s load is, without the need for Xcel to build costly new transmission or make costly transmission upgrades,” said Will Vaughan, a development manager for Renewables at Lightsource bp. “So this contributes to keeping everybody’s power prices lower.”
Construction is not expected to begin for about two years, and the company is still looking for a buyer for the electricity. The development plan calls for restoring native vegetation, managing erosion, and conserving topsoil on the former dryland farm site.
Lightsource bp also operates the 300 MW Bighorn Solar and 293 MW Sun Mountain Solar facilities in Pueblo County, Colorado, and has 33 projects operating across 11 states.
Read more here.